My Sydney

The NSW Government has made an unprecedented commitment, backed by record investment, to improving transport infrastructure to support the growth of greater Sydney and the transformation of the CBD – giving Sydneysiders a network they can rely on. 

This website will help you to learn more about our projects, including the new CBD and South East Light Rail, and find useful advice on how to move in and around the CBD.

Key dates

  • 2015
  • 2016
  • 2017
  • 2018
  • 2019
  • 4 October 2015 A new CBD bus network was introduced
  • 23 October 2015 First closure of George Street, between King and Market streets, for light rail major construction.
  • 3 December 2015 Closure of George Street between Market and Park streets for light rail construction.
  • February 2016 Start of Randwick branch light rail major construction.
  • May 2016 Start of Kingsford branch light rail major construction.
  • August 2016 Start of light rail major construction in Surry Hills.
  • October 2016 Completion of the first pedestrian zone in George Street, between King and Market streets.
  • Late 2016 Barangaroo Ferry Hub opens to customers
  • Late 2016 Wynyard Station and Museum Station upgrades complete
  • January 2017 Start of construction at Circular Quay
  • 2018 Light rail construction completed and testing begins.
  • 2019 Light rail opens to customers.